Planning

In 2021, the opportunity to maximise the capacity of the third phase of the Dogger Bank Wind Farm, Dogger Bank C, was identified. This means that additional capacity of up to 1.5GW of renewable energy could potentially be constructed in the eastern part of the original Dogger Bank C site.

Introduction

As Dogger Bank D is recognised as a strategic national asset for energy with an expected generating capacity greater than 100MW, it qualifies as a Nationally Significant Infrastructure Project (NSIP).

We will follow the procedures set out in the Planning Act 2008 which provides the framework for how NSIPs are developed. We will apply to the Planning Inspectorate, an agency responsible for managing the NSIP planning process on behalf of the Secretary of State for Energy Security and Net Zero, for permission to build and operate Dogger Bank D.

2024 Scoping Report and Scoping Opinion

On 2 August 2024 the Planning Inspectorate provided a Scoping Opinion in response to the 2024 Scoping Report submitted by the Project on 24 June 2024. The Scoping Opinion gives guidance on the scope and level of detail required for the future Environmental Impact Assessment to be undertaken for the proposals.

The documents are available below. Please note the Scoping Report has been split in to two parts to improve accessibility and download speeds.

Dogger Bank D June 2024 Scoping Report Part 1 >

Dogger Bank D June 2024 Scoping Report Part 2 >

Dogger Bank D August 2024 Scoping Opinion >

2023 Scoping Report and Scoping Opinion

The documents relating to the 2023 scoping exercise are available below.

Click here to view April 2023 Scoping Report >

Click here to view June 2023 Scoping Opinion >

Developing the Project

Protecting and enhancing the habitats we operate in as we harness the wind for renewable energy generation is a key part of developing our proposals.

We will be assessing the potential impacts of the offshore environment and of potential cable corridors and where other onshore infrastructure may be sited for the grid connection. Undertaking an EIA is an important part of the NSIP pre-application process and informs how the environment will be protected during the construction, operation and decommissioning phases. We will be looking at ways to keep disturbance to people and wildlife to a minimum.

Preliminary Environmental Information Report

We have prepared a Preliminary Environmental Information Report (PEIR) which outlines our initial findings from the EIA carried out so far. This report forms the basis of the statutory consultation. Click here to go to view and download the PEIR and associated documents.

To make the information more accessible, a Non-Technical Summary (NTS) of the PEIR is available. You can download a PDF version of the NTS or view a digital version.

Digital version

Field of Rapeseed, near Paull, East Yorkshire

What matters to you, matters to us

You have the opportunity to share your views on the proposed Dogger Bank D project. We’re keen to hear your thoughts on topics such as landscaping, protecting local views, wildlife conservation, routeing around sensitive areas, and how we keep you informed during construction and beyond, if the Project receives consent.

We’ve developed a Commitments Register - a list of proposed mitigations, enhancements, and monitoring measures - based on a series of actions and early feedback. The Commitments Register is shared as part of the statutory consultation and will continue to evolve throughout the pre-application stage of Dogger Bank D.

We’d like to hear from you: Are there any new commitments or changes to existing ones that you think the Project should consider?

Your Opinion Matters

If you would like to receive updates directly, please take a couple of minutes to register your details

Register